Last week we completed and opened 441 parking places and 12 accessible parking locations. This week’s schedule departs from the original somewhat, as we adjust to traffic flows and patterns.
Monday (yesterday), we worked in lots 13, 14 and 16. We will stripe these lots on Wednesday.
Tuesday (today), we will be in lots 11 and 12 and the inside lane of Poorman Drive, striping these on Thursday.
Wednesday, we will complete lots 9 and 10. (Striping on Friday)
Thursday we will be closing the east parking lot at Montgomery Hall and the north/south road from Montgomery Hall to the Millennium Center.
On Friday we will work on the west parking of Montgomery Hall.
Our goal this week is to have the east half of our campus completed before moving to the west section. We will continue to keep you updated as we proceed.
Thanks for your patience, as always.
Hugh Garvey
AVP Construction
786-9605 or hugh.garvey@llcc.edu